From 1 July 2025 we're changing to a fees up front payment system. This means that payment is made at the application stage and when we have granted the application we can issue it to the customer at the same time - speeding up the turnaround time on building consents. Any additional processing time (recoverable on an actual and reasonable basis, as per the Building Act 2004 s281B) and planning/engineering approval charges (if applicable) will be invoiced at the end of processing.
Appendix 9 - Banks Rd
Appendix 9: Schedules of Works
- Banks Road Structure Plan
The table below outlines the schedule of works to be undertaken in conjunction with the Banks Road Structure Plan.
Schedule of Works for the Banks Road Structure Plan
Water
- 200mm diameter water main from south-east corner of Grosvenor drive along future connection road to Banks Road.
- Extend along northern side of Banks Road to Burwood Road intersection.
Wastewater
- Sewer pump station.
- 150mm diameter gravity main (from Banks Road to the pump station).
- 225mm diameter gravity main (Longlands).
- 150mm diameter rising main.
Stormwater
- Stormwater retention/soakage trenches within the identified reserves.
- Future stormwater retention/soakage areas subject to internal roading design.
- Undertake landscaping of the reserve areas.
Roading
- Provide two north-south connections, one ultimately linking through to Mangawhero Road.
- Provide internal west-east link, being for a combination of vehicular and pedestrian use.
- Widening of Banks Road from the Burwood Road intersection to the eastern side of the site.
Provide kerbing along the northern side of Banks Road from the Burwood Road intersection to the eastern side of the site.
- Provide a footpath within the northern berm of Banks Road from the Burwood Road intersection to the eastern side of the site.
- Increase the road width of Burwood Road opposite Banks Road intersection